SHIMLA SEWERAGE PROJECT
SHIMLA SEWERAGE SCHEME FROM OPEC : 10 MILLION
DOLLARS
Shimla sewerage project is being implemented with the aid of OPEC Fund
for International Development Vienna. The estimated cost of the project
is Rs.54.80 crore. The ratio of OPEC Fund and State Share is as under
:-
OPEC Loan (73%) |
Rs. 40 crore.(10 Million Dollars) |
State Share (27%) |
Rs. 14.80 crore. |
Total |
Rs. 54.80 crore. |
The Shimla Sewerage project was started in November,
1997. The work is in advanced stage of completion. Sewage Treatment
Plants at 6 places are almost completed as per details given below:-
Dhalli (0.76 MLD ) |
Completed & commissioned |
North Disposal (5.80 MLD) |
-do- |
Summer Hill (3.93 MLD) |
-do- |
Sanjauli/Malyana (4.44 MLD) |
-do- |
Snowdon (1.35 MLD) |
Completed and tested |
Lalpani (19.35 MLD) |
Completed & commissing started from 26.7.04 |
Out of 179 Kms. sewerlines, 179.352 Kms. sewer lines
have been laid in different zone of the Shimla town.
Executive Engineer, Sewerage Network, Const. Division, Shimla-5 has
been authorized to sanction the sewerage connections to the buildings
situated outside the Municipal Corporation limits.