Major Irrigation Project Shahnehar

MAJOR IRRIGATION PROJECT SHAHNEHAR

An inter-State agreement was concluded on 4th August, 1987 between Govt. of Punjab and Govt. of Himachal Pradesh for construction of Shahnehar Project to provide Irrigation facilities for a total CCA of 15287 ha. of Himachal Pradesh falling on both banks of river Beas below the Pong Dam . This includes CCA of 3465 hect. (existing irrigated area rendered dry ) and 11822 hect. of potential irrigable area deprived of Irrigation facilities due to construction of Shahnehar barrage by Punjab Government down stream of Pong Dam.

The Project envisaged construction of two lined canals viz left bank is 33 kms. long with carrying capacity of 3.82 cums. taking off from existing Mukerian Hydel channel to irrigate 6183 ha. of land and right bank canal is 48.85 Kms. long with carrying capacity of 6.48 cums. to irrigate 9104 ha. of land. It will take off from the existing guide bundh of Shahnehar barrage to be constructed by the Punjab Govt.

There was difference of opinion between Himachal Pradesh and Punjab Engineers regarding canal capacities and water releases to be made by Punjab to Himachal Pradesh . Various meetings were held in Central Water Commission, New Delhi. Finally CWC sent a detailed note containing their recommendations to both Himachal Pradesh and Punjab Governments during 2/93. Since these recommendations were not acceptable to both Himachal Pradesh and Punjab, CWC referred the dispute to Minister of Water Resources for Arbitration during 8/93.

To settle the dispute between the two Govts. regarding sharing of the cost of the Project to be constructed for providing irrigation facilities as planned. Sh. A.B. Joshi, the then Chairman, Central Water Commission was appointed Arbitrator, who after hearing the representatives of both the govts. decided as under :-

(a) The combined capacity of the lined canal of the Project shall be 10.30 cumecs with capacity of right bank canal to be 8.50 cumecs and that of left canal 1.80 cumecs.
(b) The cost of 7.08 cumecs will be shared by Punjab and Himachal Pradesh in terms of the interstate agreement dated 4th August, 1983 and the balance cost of the difference of the capacity of channel between 10.3 cumecs and 7.08 cumecs shall be borne by Himachal Pradesh.

The award was announced on 19.05.95. The Project report was submitted to Central Water Commission on 8th Aug. 1995. The Project was finally cleared for its techno-economical consideration by the Technical Advisory Committee headed by Secretary , Ministry of Water Resources on 3rd April, 1996 . Planning Commission approved the project for the construction of two canals on left and right banks of river Beas having a total capacity of 10.30 cumecs for Rs. 143.32 crore, out of which Rs. 88.49 crores was to be borne by Punjab Govt. and remaining Rs. 54.83 crore by Himachal Pradesh Govt. Shahnehar Major Irrigation Project has been approved by the Planning Commission , Government of India for Rs. 143.32 crore on 21.2.1997. The A/A & E/S has been accorded for the Rs. 143.90 crore ( Inclusive the cost of land development of H.P. The above estimate was framed considering the base year as 1995.

In this approved Project, the annual funding by each state was proposed as under:-

Year of Constrction Amounting as per integrated Project (Rs.in Lakh)
HP Share
(Rs.in Lakh)
Punjab
(Rs.in Lakh)
1997-98
2348.25
852.20
1496.05
1998-1999
2551.04
978.88
1572.16
1999-2000
2924.98
1055.07
1869.91
2000-2001
2406.39
864.04
542.35
2001-2002
3228.18
1351.86
1876.32
2002-2003
873.16
380.95
492.00
Total
14332.00
5483.00
8849.00

The Punjab Govt. was required to release funds to the extent of Rs. 88.49 Crore against which Rs. 66.73 crore have been released as under:-

Amount released during 1986-87
Rs. 1.50 crore
Amount released during 2000-01
Rs. 2.00 crore
Amount released during 2001-02
Rs.11.00 crore
Amount released during 2002-03
Rs.15.00 crore
Amount released during 2004-05
Rs. 13.42 crore
Amount released during 2005-06
Rs. 17.99 crore
Amount released during 2005-06
Rs. 08.80 crore
Amount released during 2007-08
Rs. 04.40crore
Amount released during 2008-09
Rs. 02.33 crore
Expenditure incurred by Punjab Govt. directly in its Territory up to 3/05
Rs. 08.27 crore

PHYSICAL PROGRESS

Construction of Canal

Approved Scope (in KMS)

completed work (in KM)

(up to 8/2010)

Balance Work
Left Bank Canal (LBC)
24.600
23.425
1.175
Right Bank Canal (RBC)
45.305
25.927
19.378
Total
39.905
49.352
20.553
CCA (in Hect.)
Approved Scope

completed work

(up to 3/2010)

Balance Work
Left Bank Canal (LBC)
6183
6030.86
152.14
Right Bank Canal (RBC)
9104
3934.94
5169.06
Total
15287
10065.80
5321.20