HYDROLOGY PROJECT PHASE-II

Brief:-
 
World Bank has approved a credit of US$ 104.98 Million to the Govt of India for the Hydrology Project Phase-II. (IBRD Ln. No 4749-IN). The total cost of the Project is US$ 135.01 Million. Phase-I of Hydrology Project was implemented in the nine peninsular States of the Country & by 6 Central agencies during 1995-2003. Phase-II of the project is being implemented in 13 States including 9 States of HP-I & by 8 Central agencies. The  Project is proposed to be implemented in the State over a period of six years starting from April 5, 2006.



Aim: -
 
Hydrology Project–II aims at improving the existing system and developing an integrated and comprehensive hydrological data collection and information system in the State. The Hydrological Information System (HIS), so created , shall be of immense use for all water resource sector stake holders.

 

Project Time Frame:-
 

This project would be implemented over a period of six years. The first three years envisages for creation of infrastructure for generating the data base and the last three years are to be utilized for collection of data and it’s monitoring.

 

Cost:-
 
The Project has been approved for the State at our estimated cost of Rs.49.5038 crore. The A/A & E/S has been accorded by the Govt. of H.P. on dated 14.3.06 for Rs. 49.5038 crore.

 Category Wise Cost:-

 

 

Category

Original Cost

Rs. In Lakh

% age

MTR

Revised

Rs. In Lakh

% age

Civil Work

1359.53

27.50

1287.84

26.02

Goods

1441.88

29.10

1416.44

28.61

Consultants

96.46

1.95

74.33

1.5

Training

140.57

2.85

143.97

2.91

Inc. Operating Costs

1911.94

38.60

2027.80

40.96

Total

4950.38

100

4950.38

100

 

Component wise cost :-

 

Component 1 :

Institutional Strengthening (Rs.6.6209 Crore)
  Sub Component:   Awareness, Dissemination and Knowledge Sharing (Rs.1.0406 crore)
  Sub Component:    Implementation Support (Rs.5.5803 Crore)
Component 2 : Vertical Extension
      Pertains to HP-I States/ Central agencies.
Component 3 : Horizontal expansion (Rs.22.6048 Crore)
  Sub Component:  Upgrading of data collection net work (Rs.12.0400 Crore )
  Sub Component:

Upgrading of data processing & management system  (Rs.8.2129 crore).

  Sub Component:  Purpose driven studies  (Rs.2.0474 Crore)
  Sub Component:  Training (Rs.0.3045 Crore)
Component 4 :

Recurrent Cost (Rs.20.2780 Crore)

     


Main Activities Proposed Under HP-II.

 Component 1 :           Institutional Strengthening

I Training equipment for awareness   - 1 Set
 
II Consultancies:-    
 

i.    HIN Analysis & benefit monitoring.
ii    Web Site development
iii.   Management and monitoring (Short term).
iv.   Technical consultancy (Short term).

III Logistical support
 
i Sectional offices 42 Nos.
ii Office of Ground Water Organization(GWO) 1 No.
iii Cars 2 Nos.
iv Jeeps 24 Nos.
v Training equipments 2 set.

 

 Component 2 :              Horizontal Expansion.

                       A      Sub Component:     Upgrading of data collection net work

 
I
           
River Gauging Sites.
 

i

Frame winch  bridge outfit i/c cableway

24 Nos.

ii

Bank operated cable way

8 Nos.

iii

Discharge Measuring Weirs

3 Nos.

 
II          Ground Water Observation well
 
 

i  Ground Water Observation Wells  80 Nos.


III         Hydro meteorological Sites   
 

i Installation of Standard Rain Gauges 101 Nos.
ii Installation of Automatic Rain Gauges 35 Nos.
iii Installation of Full Climatic Stations 6 Nos.
iv Installation of Standard Snow Gauges 16 Nos.
v Installation of Weather Station 2 Nos.


IV          Water Quality Laboratories
 

i C/O Water Testing Labs Level 1 6 Nos.
ii C/O Water Testing Labs Level 2 2 Nos.
iii C/O Water Testing Labs Level 2+ 1 No.
iv GPS Portable 24 Nos.


V          Data Center Buildings 
 

i Sub Divisional Offices 12 Nos.
ii Divisional office Data Centers 4 Nos.
iii C/O State Data Center  1 No.
 

                   B      Sub Component:          Upgrading of data processing & management system 

 
1.    Data Management Computer Packages

 
i Sub-divisional packages 40 Nos.
ii Divisional packages 8 Nos.
iii  State Data processing package 1 No.
iv State Data storage package 1 No.
v  GIS Software 1 No.
vi GIS Data set 1 No.
vii Other computer packages  7 Nos.

 
 2.   Communication Facility  
 

I NICNET linkage within zone 1 Nos.


PROPOSED YEAR WISE EXPENDITURE

i

1st Year Rs. 2.19 Crore

ii

2nd Year Rs.  3.04 Crore

iii

3rd Year Rs. 4.59 Crore

iv

4th Year Rs. 9.23 Crore

v

5th Year Rs.  16.78 Crore

vi

6th Year Rs. 13.68 Crore

           
TOTAL Rs. 49.50 Crore.

 
HYDROLOGICAL DATA COLLECTOR/ USER AGENCIES IN HIMACHAL PRADESH

1 HPSEB 14 Rural Dev. Deptt.
2 Hydro Power Cos. 15 EP & PC Board
3 HPIPH Deptt. 16 Tourism Deptt.
4 Horticulture University 17  Health Deptt.
5 Agriculture University  18 .TCP Deptt.
6 Agriculture Deptt. 19 Him Urja
7 Horticulture Deptt. 20 CWC
8 Forest Deptt. 21 CGWB
9 Revenue Deptt. 22 IMD
10 Fisheries Deptt.  23 BBMB
11 Science & technology Deptt. 24 NGOs/KVS
12 Industries Deptt.  25 Professional Substitutes
13 HPPW Deptt. 26 Other Individual Users

           

Top